East–West Tie Transmission Project
Province: Ontario
City/Region: Municipality of Shuniah (near Thunder Bay) to Wawa
Image Credit: Valard
NR
Project Rank
Project End: 2022
Project Type: Transmission
Industry Sector: Energy
Project Amount: $777.1 million
Date of Completion: 2022
Funding Source: Public
Federal Funding: $$170 thousand through Indigenous Services Canada to hire a Project Manager to work with participating First Nations groups.
Provincial Funding: $777 million
Transmission Line Length (KM): 450
Previous Rankings
2022 | 68 |
2021 | 59 |
2020 | 62 |
2019 | 74 |
2018 | 77 |
2017 | 75 |
2016 | 78 |
2015 | 79 |
About The Project
The East-West Tie Transmission Project is planned to consist of a new, approximately 447-kilometre, double-circuit, 230-kV transmission line, primarily paralleling an existing transmission line corridor. The new East-West Tie will which connects the Wawa Transformer Station to the Lakehead Transformer Station in the Municipality of Shuniah, near Thunder Bay, with a connection approximately mid-way at the Marathon Transformer Station. The need for the project was established by the Independent Electricity System Operator to; (i) increase capacity to meet expected electricity demand growth in northwestern Ontario, (ii) provide two-way power flow across the tie, allowing more efficient use of generation resources, and (iii) create improved electricity system reliability, flexibility and operation. Additionally, in March 2016, Ontario declared that the construction of the East-West Tie Transmission line is needed as a priority project. Construction on the project began in October 2019. it is scheduled for completion by the end of the first quarter of 2022. As of August 18, 2021, the Ministry of Natural Resources and Forestry revoked the Implantation Order, affecting construction activities and construction work resume across all work fronts. On July 21, 2021, due to extreme fire hazard and forest fires in the area, the Ministry issued Implementation Orders prohibiting construction activities associated with the project and NextBridge temporarily suspended construction from Thunder Bay to Pic Mobert First Nation. The Order was partially revoked on August 10 and fully revoked on August 18.
Financing Detail: The East-West Tie Project is the first competitive transmission project in Ontario. NextBridge was selected in the process and designated to complete the necessary development work. Although NextBridge is a private company, the funding will be public, ratepayer dollars—subject to and approved by the Ontario Energy Board.
Project Owner: NextBridge Infrastructure, a partnership with NextEra Energy Canada, Enbridge Inc., and Borealis Infrastructure
Project/Construction Manager: Quanta Services Inc.
Engineer: Burns & McDonnell
Contractor: Valard
Environmental Services: Dillon Consulting (environmental assessment)
Other Key Players: Ontario Energy Board and the IESO; Golder-a member of WSP (environmental and social impact assessment, environmental inspection services for geotech. drilling program); Hatch (constructability reviews and access planning); Englobe
Other Suppliers: Canam Group
Legal: Gowling WLG (counsel to NextBridge); Osler; Torys (acting for the owner)
Key Players
Key Players’ recognize the organizations whose work, knowledge, and expertise go into constructing and delivering the significant projects that make our annual list.
Platinum (20+ Projects)
- Accenture
- AECOM
- Aecon
- AGAT Labs
- Aon
- Arcadis IBI Group
- CIMA+
- Deloitte
- Dentons
- Dillon Consulting
- E.S. Fox
- Egis
- EllisDon
- Englobe
- Entuitive
- EXP
- EY
- GHD
- Golder (WSP)
- Hanscomb
- Hatch
- HKA
- Infrastructure Ontario
- INTECH Risk Management
- Jacobs
- KPMG
- LEA Group
- McElhanney
- Norton Rose Fulbright
- Parsons
- PCL
- Stantec
- Tetra Tech
- TULLOCH
- Victaulic
- Wood (WSP)
- WSP
Silver (10-14 Projects)
- ACCIONA Infrastructure Canada
- Accuracy
- ACS Infrastructure
- Associated Engineering
- Bennett Jones LLP
- Bird Construction
- Blake, Cassels & Graydon
- COWI
- Davies Ward Phillips & Vineberg
- DECAST Ltd.
- HDR
- Hemmera
- Infrata
- Kasian
- LRI Engineering
- Matrix Solutions
- McMillan LLP
- Montrose Environmental
- Mulvey & Banani
- NORR Architects & Engineers Ltd.
- Osler
- Rider Levett Bucknall
- Sener SES Canada Inc.
- Singleton Urquhart Reynolds Vogel
- Tiree
- Torys
Bronze (5-9 Projects)
- Allnorth
- Amico
- Andritz Hydro Canada
- Arium Design
- Astaldi
- Bessac
- Bombardier
- Caisse Centrale Desjardins
- Cameco
- Cannon Design
- CRH Canada
- Crossey Engineering Ltd.
- Daoust Lestage
- Dexter Quebec
- Dr. Sauer & Partners
- Entro
- Flatiron
- International Bridge Technologies
- Johnson Controls
- KGS Group
- Laker Energy
- LeighFisher
- Milestone Environmental
- Modern Niagara Toronto Inc.
- Montgomery Sisam Architects Inc.
- Nu-Tech Precision Metals
- Plenary Americas
- PwC
- RBC Dominion Securities Inc.
- Siemens
- Space2Place
- STRABAG Inc.
- Turner Construction Company
- Valard
- WestPro
- Worley