Sunrise Natural Gas Processing Plant

Province: British Columbia

City/Region: Montney Region

Image Credit: Pipeline News North

NR

Project Rank

Project Type: Natural Gas

Industry Sector: Energy

Project Amount: $860 million

Date of Completion: 2017

Funding Source: Private

Private Funding: $860 million

Previous Rankings

201754
201654

About The Project

This new plant is one of three gas plants that Veresen plans on building in the Dawson Creek region. The Sunrise plant is expected to process 400 million cubic feet of gas per day, while Tower, would be 200 million cubic feet per day. The existing Saturn plant would be expanded to allow for an additional 400 million cubic feet of gas per day.

Construction of the Sunrise gas plant has commenced, with the facility expected to be service in late 2017.

Project Owner: Veresen Midstream Limited Partnership—Veresen (50%) and affiliates of Kohlberg Kravis Roberts & Co. LLP (50%)

Project/Construction Manager: Encana

Engineer: Fluor

Contractor: Ledcor

Key Players

Key Players’ recognize the organizations whose work, knowledge, and expertise go into constructing and delivering the significant projects that make our annual list.