Regina Wastewater Treatment Plant

Province: Saskatchewan

City/Region: Regina

NR

Project Rank

Project End: 2016

Project Type: Water Wastewater

Industry Sector: Water

Project Amount: $611 million

Funding Source: P3

Federal Funding: $P3 Canada Fund: $58.5 million

Previous Rankings

201674
201575

About The Project

This treatment plant will increase the City of Regina’s wastewater treatment capacity and modernize the facility through upgrades to the primary (non-organic) and secondary (organic) treatment processes and the construction of a new tertiary treatment process. The new system will provide treatment capacity for a population of 258,000 and significantly reduce ammonia, nitrogen, phosphorous, E. coli, and suspended solids levels from entering the water system. The Province of Saskatchewan has raised effluent standards to improve water quality and the environment, and to meet these new standards, a new wastewater facility is required. The new facility will be substantially complete in December 2016.

Project Owner: City of Regina

P3 Team Members/Project Team: EPCOR Saskatchewan Water Partners—EPCOR Water Services, Graham Group, Lockerbie Stanley/Aecon, and Stantec

Other Key Players: Aon (risk/insurance advisor to authority); BTY Group (independent certifier)

Legal: Norton Rose Fulbright

Key Players