Calgary International Airport Development Project

Province: Alberta

City/Region: Calgary

NR

Project Rank

Project End: 2016

Project Type: Airport

Industry Sector: Transportation

Project Amount: $2 billion

Funding Source: Private

Private Funding: $2 billion

Previous Rankings

201621
201521
201417

About The Project

The Airport Development Program (ADP) includes two major projects: the Runway Development Project (RDP) and the new International Terminal. The RDP, which includes Canada’s longest runway at 14,000 feet, has been completed and the first arriving and departing flights took place on June 28, 2014. The International Facilities Project, which will more than double the size of the existing facility, is still on track to be near construction completion in late 2015. This will be followed by a number of commissioning, activation, and integration activities that will continue through 2016. The new International Terminal is scheduled to open in fall 2016.

New elements to the program will enhance the connections processes at the airport in conjunction with the opening of the new International Terminal in These elements are focused on passenger connectivity from the existing Air Terminal Building to the new International Terminal. This includes a new secure Connections Corridor, which will allow passengers to connect from concourse to concourse without leaving the secure area. The corridor also includes three transportation options, including foot traffic, use of moving walkways, or the option to take the new Compact Transit System (a small vehicle that can carry up to 10 passengers at a time along the corridor).

Project Owner: Calgary Airport Authority

Project/Construction Manager: AECOM and Hatch (project managers on runway development); AECOM (project manager facilities); EllisDon (construction manager, airport facilities); PCL-Parsons-Dufferin JV (construction manager, runway development)

Engineer: Associated Engineering (prime consultants for runway); CH2M (sub to AE); Hatch (civil airside consultant on facilities and engineering design manager on runway development)

Other Key Players: AirBiz (airport planning consultant); LVM (quality assurance); Entro (guest experience strategy, wayfinding, and signage); Engineering Harmonics (sound and digital signage consultant); SNC-Lavalin (operational readiness and transition program); BEEI (QA); IQC (QA); WSP | MMM Group (commissioning and geomatics services); Hanscomb (owner’s design and construction stage cost consultant)

Consulting Engineers: Reed Jones Christoffersen (structural); AECOM (electrical/mechanical); Stantec (IT systems)

Architects: DIALOG Design (prime consultant for international facility)

Other Suppliers: Canam (steel joists)

Key Players

Key Players’ recognize the organizations whose work, knowledge, and expertise go into constructing and delivering the significant projects that make our annual list.