Rehabilitation of Robert-Bourassa Generating Units

Province: Quebec

City/Region: Baie-James

Image Credit: Hydro-Québec

NR

Project Rank

Project End: 2023

Project Type: Hydroelectric

Industry Sector: Energy

Project Amount: $732 million

Date of Completion: 2023

Funding Source: Public

Provincial Funding: Hydro-Québec ($732 million)

Previous Rankings

202377
202274
202172
202066
201966
201866

About The Project

Robert-Bourassa generating station is one of the crown jewels in Hydro-Québec’s generating fleet. With an installed capacity of 5,616 MW, it is the most powerful generating facility in Québec. Its longevity is essential to ensuring the long-term supply of reliable power in Québec. This project includes the rehabilitation of eight of the sixteen generating units of the Robert-Bourassa generating station, as well as the speed governors, static excitation systems and cooling systems in all sixteen units. The DEW generating units (made by Dominion Engineering Works) will be the ones rehabilitated, as they show the most signs of wear. This work will allow Hydro-Québec. to optimize its facilities and adequately secure Québec’s energy future. Project completion is targeted for 2023, which will see such milestones as the final assembly of the seventh generating unit (out of a total of eight to be replaced).

Project Owner: Hydro-Québec

Engineer: AECOM

Contractor: GE; TRANSAR

Other Key Players: EXP (plans and specs for mechanical systems); McElhanney; Englobe; WSP (engineering)

Key Players

Key Players’ recognize the organizations whose work, knowledge, and expertise go into constructing and delivering the significant projects that make our annual list.