BC Hydro has selected a new realignment for Highway 29 at Cache Creek/Bear Flat, following an extensive consultation process with Indigenous groups and local property owners.

In December 2017, the Province of B.C. asked BC Hydro and the Ministry of Transportation and Infrastructure to work with Treaty 8 First Nations and local property owners to redesign the Highway 29 realignment at Cache Creek/Bear Flat to reduce the effects on potential burial sites and First Nation identified areas of cultural importance.

The following is a description of the three realignment options that were assessed:

  • Option 1: shifts the alignment north about 170 metres from a potential burial site and 90 metres from the sweat lodge. This option has a bridge that is 145 metres longer and an additional 80 metres of road length compared to the original alignment. The additional combined bridge and road length is 225 metres.
  • Option 2: shifts the alignment even further north about 300 metres away from a potential burial site and 590 metres from the sweat lodge. This option has a bridge that is 245 metres longer and an additional 720 metres of road length compared to the original alignment. The additional combined bridge and road length is 965 metres.
  • Option 3 (selected): shifts the alignment between the first and second options about 240 metres away from a potential burial site and 370 metres from the sweat lodge. This has a bridge that is 195 metres longer and an additional 250 metres of road length compared to the original alignment. The additional combined bridge and road length is 445 metres.
See also  Preferred proponent named for Site C spillways civil works

Compared to the two other options that were considered, the selected route:

  • Has similar or lower impacts to archaeological and heritage sites, and
  • Has lesser impacts on private lands and agricultural lands than the most northern route evaluated.

BC Hydro will be continuing work for this portion of the realignment, including geotechnical investigations and drilling. Full construction for this segment of highway realignment is expected to be underway by spring/summer 2020.

Construction activities for the western four kilometres of the highway realignment at Cache Creek/Bear Flat, which is not affected by the alternate realignment options that were studied for the eastern section of this segment, will begin at the end of September 2018.

Highway 29 connects Hudson’s Hope to Fort St. John and runs along the north side of the Peace River. The creation of the Site C reservoir will require six segments of Highway 29 to be realigned over a total distance of about 30 kilometres.

LEAVE A REPLY

Please enter your comment!
Please enter your name here