By Matti Siemiatycki
Nearly a decade ago, the Institute on Municipal Finance and Governance (IMFG) published my paper, Cost Overruns on Infrastructure Projects: Patterns, Causes, and Cures. The paper was in many ways a cri de cœur, written in the language of academia. I have always been drawn to big, ambitious infrastructure projects, not just their technological and engineering marvels, but the way that, if done well, they form the basis for sustainability, economic prosperity, social equity, and a high quality of life.
Yet megaprojects have an Achilles heel: they invariably go over budget and miss deadlines. This trend represents not only a colossal waste of money, but it also erodes public trust in the power of governments to solve complex challenges. In my beloved hometown of Toronto, I have seen one big ambitious project after another go sideways. In 2015, blown budgets in the redevelopment of Union Station and the Spadina Subway extension to York University and Vaughan were capturing the public’s attention.
To channel my own frustration at the situation, I drew on the best scholarly evidence then available to explain how prevalent cost overruns were, identify their root causes, and describe solutions used in other countries to address the problem. The IMFG paper was an attempt to give Canadian leaders a playbook to understand and address cost overruns in a serious and evidence-based way.
In the section on the patterns of cost overruns, I showed that Toronto and Ontario were far from alone in facing mega cost overruns on megaprojects. It was a global problem, common to big projects in all major infrastructure sectors. The causes I identified, based on the literature, were a mix of technical difficulties, optimism biases, and strategically misleading behaviour by politicians to advance preferred projects. Individuals and organizations tend to overestimate their own skill and the level of control they have over a project outcome while downplaying risks. At the same time, there are many incentives for politicians and firms to deliberately underestimate project budgets to gain public support, receive approvals, or win a contract, as projects are rarely cancelled once construction begins.
In proposing solutions, I emphasized that the world was in the midst of a data revolution in which enhanced performance monitoring and predictive analytics could detect problems early on and help improve delivery. I was a few years too early for the artificial intelligence (AI) revolution, but the seeds were there. I also suggested creating systems to reward good performance by contractors, enhancing public-sector management capabilities through the creation of leadership training programs as done in the United Kingdom, applying state-of-the-art forecasting techniques, and selectively using public-private partnerships that were more limited in scope than those typical of the time.
Fast forward nearly a decade. The more things change, the more they remain the same. The projects under scrutiny may have changed, but alas, the situation is largely the same. Today it is the Eglinton Crosstown, Finch LRT, and Ottawa LRT that symbolize project delivery mismanagement. And politicians and infrastructure executives continue to express outrage at the fact that prominent megaprojects are late and over budget.
Few of the tangible steps recommended in the IMFG paper 10 years ago to reduce cost overruns have been meaningfully acted upon. There is no systematic performance monitoring or information sharing across the sector. No structured system has been created to reward good contractor performance in procurement. Forecasting remains opaque and project documents are sometimes released after, rather than before decisions are announced. The U.K.-style training academy model for leaders of major projects has been launched in Australia and Hong Kong, but not in Canada—yet. There is industry and academic interest in developing such an academy in Toronto, so perhaps we shall see some progress in this area.
One change is that the fully bundled, design-build-finance-operate-maintain–style public-private partnerships so popular in the early 2010s have fallen out of favour. They are too expensive, and the risk transfer mechanisms have not held up when stressed, leading to increased costs. In many cases it has been the private sector that has pulled back from these fixed-price contracts for complex megaprojects, finding that the risks of major cost escalations were simply too great.
There is considerable industry uncertainty about what will come next. Governments are increasingly unbundling contracts into smaller pay-for-performance packages and using models such as progressive design-build and alliances that use joint management and deep collaboration between the parties to share rather than transfer risk. Time will tell whether these emerging models deliver better results.
Cost overruns continue to plague large infrastructure projects in Canada. And Canada has been identified as a high-cost jurisdiction for building infrastructure, just as we are seeing the biggest building boom in a generation.
While procurement models are evolving, Canada has not adopted other tools and techniques to improve infrastructure project delivery and cost certainty. For Canadians, a key question endures—when will we stop the charade of being upset with over-budget, late megaproject delivery, and take real steps towards reform? We can only hope that in another 10 or 20 years’ time, we are not still having the same conversation.
This article is published with the permission of The Institute on Municipal Finance and Governance (imfg).
Matti Siemiatycki is a leading expert in infrastructure planning and policy, and a Professor of Geography and Planning and Director of the Infrastructure Institute at the University of Toronto.
[This article appeared in the July/August 2025 issue of ReNew Canada.]
Featured image: (Metrolinx)










We here in Canada have looked to ongoing operational entities like Infrastructure Ontario and Metrolinx to manage dozens of mega-projects at once. But enormous projects are unique multi-billion-dollar enterprises, each one completely different from the last. Each enterprise’s mission, management team, market conditions and the environments they must contend with are unique for that project and time. Trying to manage all of these enterprises using standard templates, organizations and processes is a recipe for disaster.
Management agility, the ability to adjust course and make decisions quickly based on new unexpected conditions is essential for the success of any individual mega-project. Bureaucracies managing a series of these endeavours cannot hope to be successful using standard processes, organizational structures and templates for all their mega-projects.
A better model might be to do what Warren Buffet does with his portfolio of companies at Berkshire Hathaway.