Vancouver’s new Fire Hall 17 reflects the city’s design challenge to build a structure that meets the design certification requirements of the Canada Green Building Council’s Zero Carbon Building Program, one of 16 such pilot projects in Canada. The partners are also pursuing LEED Gold certification and, if approved, the building will be the first fire hall in North America to attain Passive House certification. These ambitious targets were set to align with the City’s sustainability policies. According to HCMA Architecture and Design, the building will reduce operational carbon emissions by 77 per cent compared with the fire hall it is replacing.

The 1,800 square-metre facility comprises four drive-through apparatus bays, accommodations for two firefighting crews and offices in the main building, and a six-storey hose storage/training tower. Like all fire halls in Canada, the facility will serve as a post-disaster emergency hub, which requires a resilient building that can withstand seismic events.

To meet the seismic requirements of Canada’s National Building code, the building has a stout reinforced concrete structure with a structural steel frame for portions of the third level. The main building is clad in brick and metal panels that cant outward at the base giving the form a strong and sturdy presence.

Schöck Isokorb concrete-to-concrete structural thermal break transfers bending moments and shear forces, while preventing heat energy waste, chilled interior floors, and formation of condensation and mould. (Schöck North America)

Mitigating exterior and interior thermal bridging

Central to meeting zero carbon goals is the building’s high-performance envelope, which wraps reinforced concrete walls with a 20-centimetre-thick layer of mineral wool board having an R-value of 33, and an air barrier that allows a scant 0.6 of air change per hour at 50 Pascals of pressure.

See also  New partnership to advance low-carbon concrete production

However, structural concrete and steel elements that penetrate the envelope between the main building and tower, maintained at dissimilar temperatures, would allow the unabated passage of heat energy, absent a thermal bridging solution.

“The fire hall has two thermal zones: the administrative offices and living spaces set to 20˚C (68˚F), and the ground-level apparatus bay and training tower set to 10˚C (50˚F),” says Elise Woestyn, Passive House consultant with HCMA Architecture and Design. The structures share a concrete frame at ground level and are connected by combinations of steel frame and concrete bridges on levels two and three, and a steel frame at level four. Due to the temperature differences, the designers needed to thermally isolate the two zones, while maintaining structural continuity.

“Our need to address thermal bridging led us to structural thermal breaks,” adds Federica Piccone, architect with HCMA Architecture and Design.

The fire hall has a sturdy concrete structure that serves as an armature for a steel frame on the upper levels where the exterior walls slope toward the central tower. (Schöck North America)

At the connection points, the design team specified Isokorb concrete-to-concrete and concrete-to-steel structural thermal breaks from Schöck North America. Each concrete-to-concrete module consists of a rigid foam block penetrated by stainless steel rebar that is tied into rebar on both sides of the slab or wall before concrete is poured conventionally. Each concrete-to-steel structural thermal break includes stainless steel rebar projecting from one side of the module that ties into rebar of the interior slab, and stainless steel threaded rod projecting from the opposite side of the module that bolts to exterior steel 
beam flanges.

Three concrete balconies also project from the tower’s facade. Concrete-to-concrete thermal breaks were installed between each balcony and interior slab to mitigate thermal bridging, while withstanding the rotational and shear forces created by 
these cantilevers.

See also  New Cowichan Secondary School breaks ground

In addition to reducing heat energy loss, the structural thermal breaks prevent concrete structures on the warm sides of both the exterior and interior walls from becoming chilled, reaching dew point, or supporting mould growth.

Installed between the concrete-to-concrete thermal breaks are special Isokorb thermal breaks that resist seismic shear forces in compliance with National Building Code of Canada 2010 standards for seismic resistance.

“The most unusual application for structural thermal breaks was a high parapet wall at the top of the tower,” says Meredith Andersen, associate engineer with RJC Engineers. The parapet changes in height from about 1.2 to 4.3 metres as the top of the building steps down behind it.

A parapet is essentially a vertical cantilever and, because of its height, can encounter significant moment, shear and seismic forces. Concrete-to-concrete thermal breaks were aligned horizontally at each “step” and vertically in the plane of the wall to prevent thermal bridging.

Other energy-saving measures

The high-performance building envelope allowed the designers to reduce the size of the building’s heat pump to one-fifth of that needed for a comparable code-compliant building in Vancouver. The heating/cooling system is supplied by a high efficiency ground-source heat pump served by 15 geothermal bore holes. An 80 kW solar panel array supplements electricity and six energy recovery ventilators transfer heat from outgoing interior air to incoming fresh air, reducing the required capacity of the HVAC system.

Overall energy savings allowed the designers to include elements that reduce energy loads further such as electro-chromatic glass that blocks heat gain and glare by becoming translucent when activated.

See also  Canada announces major renovation of Arthur Meighan Building

“This project responds to the urgency of the climate crisis,” says Darryl Condon, managing partner at the Vancouver architecture firm HCMA. “It shows that even large, complex facilities can lead the way in reducing our industry’s carbon footprint, while still improving the public service they provide.”

Adds Danica Djurkovic, director of Facilities Planning and Development at the City of Vancouver: “This community facility is a leading example of the City of Vancouver’s climate commitments, showing that we can make near zero-emissions buildings the new normal, while enhancing occupant comfort, and reducing energy and water consumption costs.”

This case study was submitted by Schöck North America.

[This article originally appeared in the November/December 2021 edition of  ReNew Canada.]

Featured image: The main building at left and the training tower at right are structurally integrated on four levels but thermally isolated with Isokorb concrete-to-concrete and concrete-to-steel structural thermal breaks. (Schöck North America)