City Council has approved a budget and phased plan for building the new Granville Bridge Connector (GBC) project and improvements for Drake Street in Vancouver, British Columbia.

The combined project will result in a safe create a safe, accessible, walking and cycling connection across the Granville Bridge. The connector and improvements are essential for accommodating the growing number of people living, working, and playing in the city and region, and helps meet the city’s Climate Emergency Response transportation targets.

Due to the financial pressures of the COVID-19 pandemic, council voted to reduce funding for the first phase of GBC design and construction to $12.5 million, narrowing the scope to focus first on much-needed pedestrian and cycling safety and accessibility improvements to the bridge. The capital budget had previously earmarked $25 million for the first phase.

“The pressures on the City’s budget due to the effect of the COVID pandemic are substantial and yet the improvements to the Granville Bridge and Drake Street identified in this first phase are critical to Vancouver,” said Vancouver Mayor Kennedy Stewart. “Providing safe, sustainable, and accessible ways to cross the bridge is essential, particularly in light of a growing city and region facing a climate crisis.”

Granville Bridge was designed to connect to high-speed, high-volume freeways that were never built. The freeway-style design presents significant safety and accessibility challenges, including narrow and uncomfortable sidewalks and barriers to people using mobility aids.

Conceptual plans for an improved walking, rolling, and cycling path across Granville Bridge.

The first phase of construction will be an interim design that:

  • Creates safe and accessible walking and cycling paths on the west side of the bridge by:
    • Reallocating two of the eight existing traffic lanes
    • Adding a concrete barrier to provide protection from motor traffic
    • Adding signals to the crosswalks at the Fir and Howe ramps
  • Connects with the Arbutus Greenway on the south side of the bridge via:
    • Modifications to the loop at Granville Street and 5thAvenue
    • A new traffic signal at 5thAvenue and Fir Street
    • Wayfinding signage
  • Connects with the downtown cycling network via a new protected bike lane on Drake Street between Hornby Street and Pacific Boulevard, which is achieved by converting Drake Street to one-way for vehicle traffic from Hornby Street to Hamilton Street.
See also  McKenzie Interchange final phase underway

In 2016, 18,000 residents and 17,000 jobs were within a five-minute walk of Granville Bridge and 90,000 residents and 125,000 jobs were within a five-minute bike ride. Despite being a direct route to and from downtown for many, few people use the bridge’s sidewalks or bike or because they feel unsafe and uncomfortable or because it is not accessible.

Once the Granville Bridge Connector is completed, all three False Creek bridges will offer safe and accessible options for commuting.